NEW QUESTION # 65
The supply plan is not very reliable. Components often arrive early or late. A team of planners, buyers, marketers, product engineers, and materials managers are tasked to investigate. They list several possibilities that could explain their plan's poor results.
If you were a member of the investigation team, which step would you recommend to help troubleshoot this serious issue?

  • A. For inaccurate quantity-on-hand issues, use the Planning Advisor to identify inventory accuracy improvement opportunities.
  • B. For incorrect or incomplete bills of materials, use the Planning Advisor to identify bill of material anomalies.
  • C. For incomplete or unreliable demand schedules, use the Planning Advisor to identify forecast accuracy issues.
  • D. For incorrect or unreliable supplier lead times, use the Planning Advisor to determine lead time accuracy.

Answer: C

Explanation:
Supplier lead times directly impact the reliability of a supply plan. Using the Planning Advisor to assess lead time accuracy can help identify inconsistencies in expected delivery times, enabling the team to pinpoint and resolve these issues. This approach is supported by Oracle Planning and Collaboration Cloud guidelines for troubleshooting supply chain challenges MY ORACLE SUPPORT
.


NEW QUESTION # 66
Which three are features or functions of Receipt Accounting?

  • A. If you do accrue at receipt, an accrued liability account is credited when the goods are received.
  • B. Receipt Accounting performs the accrual accounting for all receipts: services, supplies, project materials, and inventory.
  • C. Based on GAAP rules, Inventory items can be accrued at receipt or Period-end.
  • D. If you do not accrue at receipt, an accrued liability account is credited when the goods are received.
  • E. The Receipt Accounting process creates accounting distributions and posts those to Subledger Accounting (SLA) for processing and then into the General Ledger (GL).

Answer: A,B,E


NEW QUESTION # 67
Each of your planners is responsible for a different geography and set of product lines, so each planner needs to see just their own set of data, analyses and dashboards.
How do you configure the application so each planner can have their own custom dashboard viewable only to themselves?

  • A. Create public page layouts that are tailored to specific business needs.
  • B. Create private page layouts that are tailored to specific business needs.
  • C. You cannot create custom dashboards by user.
  • D. Enable layout security checkbox in the Administer Planning Security

Answer: B


NEW QUESTION # 68
You are defining material planners for your organization. However, when you go to Manage Material Planners, your organization does not appear in the list of values. Why?

  • A. The organization must be enabled in Manage Planning Profile Options.
  • B. You do not have data access to the organization.
  • C. The organization was not enabled for collection under Manage Planning Source Systems.
  • D. The organization must be enabled in Manage Planning Parameters.
  • E. The organization is an Item Organization.

Answer: C


NEW QUESTION # 69
Which two statements regarding the Decomposition scheduled process are incorrect? (Choose two.)

  • A. It received supplier commits.
  • B. It creates or updates an order forecast, used by Supply Chain Collaboration to publish to suppliers.
  • C. It does not recognize forecast exceptions.
  • D. It reads published planning data from interface tables.

Answer: A,C


NEW QUESTION # 70
As the planner, you have made some changes to a few of the specifications for items in your simulation sets. You would like to run one of your existing Demand and Supply Plans that contains this simulation set to see how these changes impact the plan.
Which option shows the steps you must complete in order to ensure that when you run your existing Demand and Supply plan, it contains your changes to the simulation set?

  • A. You are only able to update one item attribute at a time. Since you have changed multiple attributes, you will be unable to update and run this plan.
  • B. When the Demand and Supply Plan is run, verify that 'Refresh with current data' is selected in the Details section.
  • C. No additional steps are necessary. Any plans that contain your simulation set will automatically be updated with the changes.
  • D. When the Demand and Supply Plan is run, verify that 'Recalculate Safety Stock' is selected in the Details section.

Answer: B


NEW QUESTION # 71
Which disaggregation methods are used for each of these measures: adjusted shipments forecast, target service level, and shipments forecast?

  • A. Adjusted shipments forecast uses measure, target service level uses same value, and shipments forecast doesn't have any disaggregation method.
  • B. Adjusted shipments forecast uses measure, target service level uses equal, and shipments forecast doesn't have any disaggregation method.
  • C. Adjusted shipments forecast uses equal, target service level uses same value, and shipments forecast uses measure.
  • D. Adjusted shipments forecast uses proportional, target service level uses same value, and shipments forecast uses measure.
  • E. Adjusted shipments forecast uses measure, target service level uses same value, and shipments forecast uses self.

Answer: E


NEW QUESTION # 72
What are two characteristics of an 'Item' organization? (Choose two.)

  • A. It requires financial and accounting setups.
  • B. It includes parameter definition, including lot. serial number, and item sourcing rules.
  • C. It does not physically of financially track material storage or movement.
  • D. It is ideal for deployments where inventory management may not be installed.

Answer: C,D


NEW QUESTION # 73
Which is NOT a legitimate way to launch a plan?

  • A. When editing plan options, click Save and Run.
  • B. From Manage Plans, select a plan in the search results, and select Run Plan from the Actions menu.
  • C. From Setup & Maintenance, in the Planning functional area, select a plan and click the Run icon.
  • D. Launch via a scheduled process.

Answer: C


NEW QUESTION # 74
Your customer has loaded shipment history of 1/1/14 through 12/31/16 and wants to generate a monthly forecast of 1/1/17 through 12/31/17 based on two-year shipment history.
When creating a demand plan, which two plan scopes and demand plan options should your customer use? (Choose two.)

  • A. For demand plan option, add forecast shipments as forecasting profile, and enter historical buckets as 24.
  • B. For demand plan option, add forecast shipments as forecasting profile, enter historical buckets as 24, and enter forecast buckets as 12.
  • C. For demand plan option, add forecast shipments as forecasting profile, enter history start date as 1/1/15, enter history end date as 12/31/15, and enter forecast start date as 1/1/17.
  • D. For plan scope, select plan horizon days as 365, forecasting calendar as Gregorian, and forecasting time level as month.
  • E. For plan scope, select plan horizon as 12 months, forecasting calendar as Gregorian, and forecasting time level as month.
  • F. For demand plan option, add forecast shipments as forecasting profile, enter history start date as 1/1/15, forecast start date as 1/1/17, and enter forecast end date as 12/31/17.

Answer: B,D

Explanation:


NEW QUESTION # 75
A supply plan has just been run that contains a configured item. You notice that the sourcing rules of the base model were used instead of sourcing rules for the configured item. Why did this happen?

  • A. It is not possible to create sourcing rules for the configured item; all configured items always use the same sourcing rules as the base model.
  • B. The sourcing rules of the base model had a priority of 1, while the sourcing rules of the configured item had a priority of 2.
  • C. No sourcing rules have been defined for the configured item.
  • D. No planning percentages were defined at the operation level within the work definition.
  • E. The sourcing rules of the base model overrode the sourcing rules of the configured item.

Answer: C


NEW QUESTION # 76
You are setting up the plan page layout for your customer.
In which of these requirements would you use an Infotile?

  • A. Showing a breakdown of exception in a pie chart
  • B. Showing inventory value across time
  • C. Showing customer demand trend over a specific time period
  • D. Showing on-hand value compared to targets
  • E. Showing inventory values by product category

Answer: B


NEW QUESTION # 77
You've decided to opt into the Customer Demand Collaboration feature. Which three statements describe what that enables?

  • A. The information they share with you is informational and only available to you in the portal.
  • B. You can post to the portal your statistical forecast for the products you sell them so they can see your forecast for them.
  • C. A customer can use B2B messaging to share their expected needs and historical consumption for the products you sell them.
  • D. A customer can log in to a portal and manually enter their expected needs for the products you sell them.

Answer: B,C,D

Explanation:
Enabling the Customer Demand Collaboration feature allows customers to share demand data through B2B messaging or by manually entering it via a portal. Additionally, it supports sharing your forecasts with them, enabling a collaborative planning approach that enhances demand visibility and aligns expectations MY ORACLE SUPPORT
.


NEW QUESTION # 78
XYZ Company ships products globally. A warehouse in each country ships to customers in that country. When supplies are short, XYZ's constrained plan invokes an upgrade policy wherein they ship a higher value product instead of the customer's originally requested item. Although costly for XYZ, this upgrade helps maintain high customer satisfaction and on-time delivery. However, because of local preferences for some new products, this global upgrade policy no longer applies.
What is the solution?

  • A. XYZ should enable the "local end-item substitution" Decision Rule.
  • B. XYZ should keep the "end-item substitution" Decision Rule enabled and then just undo the substitutions where inappropriate.
  • C. XYZ should create local substitution rules in Product Information Management.
  • D. XYZ should disable the "end-item substitution" Decision Rule and then handle substitutions manually.

Answer: C

Explanation:
To manage the changing customer preferences for local products, creating specific substitution rules in Product Information Management (PIM) allows XYZ to customize substitutions at the local level rather than relying on a global substitution policy. This flexibility enables the company to align its policies with regional preferences, enhancing customer satisfaction while controlling costs MY ORACLE SUPPORT
.


NEW QUESTION # 79
You analyzed your customer's shipment history data at item and organization level. You found that the customer has many new products with limited history.
Does Planning Central support forecasting products with limited history, and what is this process called?

  • A. Yes, Planning Central supports the Regression for Sparse Demand forecasting method, typically used for new products.
  • B. Yes, Planning Central supports the Holt Exponential Smoothing forecasting method used for newly introduced products.
  • C. No, Planning Central does not support the Holt Exponential Smoothing forecasting method.
  • D. No, Planning Central does not support the Croston Method for Sparse Demand forecasting method.
  • E. No, Planning Central does not support the Regression for Sparse Demand forecasting method.

Answer: B


NEW QUESTION # 80
Which is the correct sequence of possible solutions that a constrained plan might consider when attempting to resolve a capacity or resource overload?

  • A. First alternate resources, then substitute components, then alternate work definitions and item structures, and finally, alternate suppliers and source organizations.
  • B. First subscribe components, then alternate resources, then alternate work definitions and item structures, and finally, alternate suppliers and source organizations.
  • C. First alternate item structures, and work definitions, then substitute components, then alternate resources, and finally, alternate suppliers and source organizations.
  • D. First alternate suppliers, then alternate resources, then substitute components, then alternate work definitions and item structures, and finally, alternate source organizations.

Answer: A